Estimated Construction Cost:
Project Funding Sources:
Federal Grant Funds
City of Cleveland Local Funds
Cleveland City Council Representatives:
Jenny Spencer, Council Member, Ward 15
Project Schedule:
Design Complete: March 2021
Award: April 2021
Construction Begins: June 2021
Construction Complete: November 2021
$3,622,000
The Proposed Improvements on
Lake Avenue will Include:
-
Complete asphalt resurfacing, including full and partial depth pavement repairs where needed.
-
Sidewalk, ADA-compliant curb ramps and drive aprons as necessary.
-
Installation of pedestrian refuge islands at West 110th Street, along Lake Avenue from Clifton Boulevard to Viking Court and at West 78th Street.
-
Revised pavement markings from Clifton Boulevard to Detroit Road (Section 2) to accommodate on-street bicycles, with exclusive bike lakes in both directions.
-
Improved pedestrian crossings, including installation of rectangular rapid flashing beacons (RRFBs) at West 85th Street and West 78th Street.
-
Project will include pedestrian refuge islands.